Shepherds Hut Deluxe Review

Hi everyone – It’s been some time, hasn’t it?

Now that the seasons are changing it’s starting to get quieter for this industry, but we do still have customers installing their cabins! For example, Mr M’s installation of their Shepherds Hut Deluxe to which he kindly sent in some images along with some commentary and tips for future installers.


Mr M writes as follows: 

A stable-full of beams and panels. Get it all under cover if possible. We started off by completing the base after correcting the three warped centre joists with modded joist hangers.  Note the bases – just paving slabs laid on a bed of sand.  Nearest is a thicker cast concrete slab also laid on sand to correct for the slope away from the wall.

Shepherd Hut Deluxe Base

Extra joist hangers were needed to correct 20 degree warp in the beam. Tuin supply 18 but you will need 10 or 12 more if your beams are not straight. Ours were cut-down joist hangers (they are only twisted plates) – not brilliant quality but good enough.  Not sure if Tuin could sell you more of the real thing, I didn’t ask. (Note: We do sell joist hangers)

This slideshow requires JavaScript.

This is by far the most tedious part of the build

Shepherd Hut Deluxe - Staining

Apply preservative and stain/paint as many parts as practicable before assembly – pay particular attention to the end grain.

Flooring goes on late into the evening    note two teenage helpers; almost as essential as the tea and hammers. Also note the clamps – you will need them. We are using cut-clasp nails.  You will need roughly three packs – 14 nails in each board.  It may sound overkill but it makes the base really secure, better safe than sorry.

Shepherd Hut Deluxe Flooring

Sides are on in the next image, as are the steps and the door hinge beams. Pay close attention to getting the hinge beams vertical in all planes prior to the roof going on or the doors will be skew-whiff.

Shepherd Hut Deluxe Walls

The roof and doors are on the next picture, I did the doors first as the roof will get in the way.  The roof is easier than expected, just keep it all tight at first with your sash cramps to keep it nice and square.  This is a month or so after the previous pic – I fell off our original step ladder adding the first feather roof beam and cracked a rib.  Highly recommended replacement cherry-picker ladder featured!

Shepherd Hut Deluxe Doors

The completed hut.  Looks good doesn’t it? The picture was taken after first frosts of the autumn (October 5th). I haven’t added the eight end roof arcs yet. We plan to add a wriggly tin roof eventually, and the roof arcs will finish that off nicely. 

Note replacement glass fibre reinforced felt laid across the arc – there are six pieces all glued and clout-nailed with the overlap away from the prevailing wind – important in Highland Perthshire! Laying it this way uses less felt and we think looks better than length-wise. It is certainly easier to do as it has no tendency to want to slide off. I suggest that you check YouTube shed covering videos which show a proper drip edge rather than wrap the covering round the roof edge as the instructions show – that will encourage the rain water to travel up to the sides of the hut via capillary action and you don’t want that. 

The completed Shepherds Hut Deluxe


Some very handy tips in this review, though we are sorry to hear about your step ladder incident – I hope it healed nicely! The end product shows how perfectly the Shepherds Hut Deluxe fits in with its surrounding garden, truly marvelous! Thank you again for sending this in.

Interested in more reviews like Mr M’s? You can find more with a range of cabins at: Tuin Pictorial Customer Reviews.

Gijs Log Cabin Customer Review

Hi everyone,

The heatwave continues to beat our expectations – And so do our customers! Installing their Log Cabins in this heat, determined to see the finishing result. For example, Mr S’ installation of their Gijs Log Cabin. With plenty of pictures to back up his words, but need I say more? Lets read what Mr S has to day about our Log Cabins.


Mr S writes as follows:

I chose to buy the Gijs from Tuin for a few reasons, I’ll list them in case it helps anyone else.

  •  Design – loved the size of Gijs with the overhanging canopy
  • Value – You get a lot for your money and the free shingles offer was great
  • Floor – I wanted to do my own thing and they didn’t force me to buy one from them
  • Website – I love all the reviews, advice, blog, instructions etc on the website. By far better than anyone else in this market.
  • Service – They look like a company that cares about their customers. They do, I have been very impressed.

I wasn’t disappointed and would thoroughly recommend this cabin.

I thought I would contribute to the website by offering my thoughts on the build process, and some photos. I hope someone finds this interesting or useful.

Foundations

I have a sloping area at the back of my garden where the cabin was going. I really didn’t like the idea or expense of excavating and laying a concrete slab so having read the website advice and doing some other homework decided to use pads with a wooden framework on top. I also wanted to install a decking area under the canopy so the foundations I needed were almost 6m x 6m.

Gijs Log Cabin Base

I used 2 different kinds of pads. 6 of them (4 corners of the cabin plus middle of the front and back walls) were excavated to about 30cm deep by 50cm square, then filled with concrete. I then sank a couple of those hollow construction bricks into the concrete and filled the holes with concrete. The other pads (about 16 of them) were expected to take less load, so I made these by laying some sharp sand and placing a concrete paving slab on the sand, then building up from there using dense concrete bricks. I didn’t bother using mortar – I’m no brickie and my builder friend said they would be fine! If you are using a similar method I strongly recommend taking time to ensure they are all level, it saves a lot of time and hassle later on.

After this I put a layer of weed suppressing cloth down so hopefully nothing will grow underneath.

Gijs Log Cabin Base

I then built the frame using treated 2 x 6″ timber from the builders merchant. I put a double thickness on the edges where the cabin walls would be. Possibly overkill but I like things to be solid. I needed to use a few wedges here and there to make sure there was contact between all points on the frame and the pad foundations. At this stage I also build the frame for the stairs that will lead up to the deck.

I am a relatively keen DIYer and found the foundation stage hard work physically, but quite rewarding. I haven’t built any foundations before, and had to put up with some sass from my builder friend who thought I’d over-engineered everything. He may be right.

Cabin Build

I have helped a friend build a similar cabin so knew roughly what to expect. First stage was delivery.

Log Cabin Delivery

Unfortunately my drive is too narrow for the fork-lift which is 3.8m wide so we had to leave it on the road. The driver was very helpful and the communication about delivery dates and times excellent. Unfortunately this left me with the task of shifting everything to the back of my garden quickly before I got a parking ticket. Fortunately my son had just finished his GCSEs and was willing to help – for some pocket money…

I made one mistake at this stage. I stacked everything horizontally at the bottom of the garden except the doors, which I stood in the house for a couple of days before the build. It was only after they warped that I read the advice on storing them flat. Store them flat!

The build is really straight forward if there are two of you – more pocket money for my son. Some of the wall pieces were hard to get in due to warping but could be fixed with some clamping and hammering as advised in the build video.

This slideshow requires JavaScript.

We had the walls and about 1/3 of the roof completed on the first day. Be very careful of the ends of the apex pieces. They are held on by a very thin strip of wood and break easily. I broke two of them off. It didn’t make a difference to the build and I was able to stick them back in place for the cosmetic look after it was finished. One problem I had was getting the purlins to sit flush with the walls. Mine were a bit warped and didn’t sit all the way down. The website advises getting a plane out, but I wasn’t too happy about that. I ended up coming up with my own solution of laying draught excluder tape along the front and back walls so that when I added the roof beams, it closed all the gaps. There’s certainly a better solution to this, but it seemed to work for me.

This slideshow requires JavaScript.

Roof

Finishing the roof seemed to take ages, but I was very glad I owned a nail gun. Mine’s a weedy electric one so I alternated between the proper clout nails and my nail gun to make sure it was solid. I then cracked on with laying the roof shingles. Again I found this quite straight forward, just a little time consuming.

I decided against insulating the roof because I’ll mainly be using the cabin as a workshop and I don’t get cold easily. What I didn’t consider however is heat! We’re in the middle of the 2018 heat wave and the black shingles act like a giant radiator – the roof is hot to the touch on the inside. Maybe next time I might put a layer of insulation up there.

Gijs Shingle Installation

Floor

I did decide to insulate the floor. I cut OSB board to hang between the joist then cut up sheets of expanded polythene to fit into the voids. Over that went a layer of plywood screwed to the joists, then an engineered wood oak floor that clipped together really easily. It looks lovely.

This slideshow requires JavaScript.

Finishing

After quite a few test pots we finally opted to use Sikkens HLS (1 coat) and Sikkens Cetol 7 (2 coats) in light oak. It has a slight gloss/silk sheen to it which I like but won’t appeal to everyone.

This slideshow requires JavaScript.

Final thoughts 

An excellent product from Tuin at a very reasonable price. The quality of the boards was excellent with a handful of warped ones. Service, before during and after has been outstanding and I wouldn’t hesitate to recommend Tuin or this cabin. If I were to do anything different in the build process I would spend more time getting the foundation pads exactly in the right place, square and level. A couple of mistakes cost me some time and headaches later in the build (including the use of a car jack to lift one corner up while I put in some shims!). Best of luck with your builds!


A very appropriate treatment choice for this Gijs Log Cabin and a beautiful setting to pair with it! Thank you to Mr S for sending in their honest review of their experience with installing their Log Cabin.

Interested in more reviews like Mr S’? You can find a load more at: Tuin Pictorial Customer Reviews.

Jenny Log Cabin Review

I’ve been so excited to share this with you guys since I’ve seen this come through in my email, so thank you to Mr T for sending this in and making a bright situation in such gloomy weather. Lets see how they turned their Jenny Log Cabin into a Cabin you couldnt miss from a mile away!


Mr T writes as follows: 

This is my overview and review and of my Jenny Log Cabin build, from Tuin.

I took a long time deliberating between different type of Cabin; sizes, profile, make and design and eventually settle for a Jenny Log Cabin from Tuin. It is 4.5 x 3.5m, which is slightly better in my opinion than the original 5.0×3.0m I was thinking of. The more square layout gives better usable space IMO.

I opted for the Jenny for the combination of design (I wanted a reverse apex design as it gives a better “frontage” yet doesn’t appear overly large), thickness of logs and Georgian-style doors and windows. It was going to be my garden gym, which probably mean it will be a summer playroom for me and the boys.

The seed started when we first move here just over 3 years ago. The garden was very overgrown with some very unkept Cherry Laurel that have overtaken almost a third of our garden. Hidden within this was a 6×10′ shed which has seen better days. We decided that it needed replacement. However, the shed stood on a concrete foundation that must have been created after the laurel have had many years to spread out. As such it was awkwardly positioned well out into the middle of our garden, to one side. Keeping a shed there will not do at all and we also wanted something a bit better – much better. Our search expanded to log cabins and that was when it all started.

Having chosen the Jenny, we needed to expand the concrete foundation as the existing foundation was too small. We toyed with the idea of just adding to the existing foundation but given its undesirable position, we ended up needing a new foundation entirely. A tradesman was called in for this and, given we would still need a shed of some sort, we wanted to have a single foundation that would cater for both the Jenny and a shed next to it – efficiency is the buzzword after all, especially since the tradesman will be doing this at the same time.

Anyway, back to the real story about Jenny. The package arrived well packaged delivered by a large articulated HGV straight from Holland with a forklift attached. It scared the neighbours silly when the forklift drove down our road with the package (5m long) across the road but luckily the forklift has some amazing manoeuvrability and the package was neatly deposited on our drive. It did stay there for a couple of weeks untouched as I needed to ensure the space was ready to receive it.

The Packaged Jenny Log Cabin

When there was finally a good weekend-weather window the job begins. On unpacking and taking inventory, there were quite a few “additional” planks which were used to securely package the items. However, this also makes it quite a challenge to determine which are originals and which are packing planks.

As usual, some of the wall log pieces were a bit warped but the video from Turin reassured me that this is quite normal as there are techniques to deal with warped wall planks since they interlock.

There were also a couple of very long (5m) square planks which, for whatever reasons, were extremely warped but at the time I thought little of them thinking there will no doubt be ways to deal with them. These were in fact the eave slats for the roof (used to stiffen the edge of the roof board and provide a surface to nail the fascia covering) as I later discovered and turns out to be a much bigger problem than I anticipated

This slideshow requires JavaScript.

So first step was to lay the foundation beams. I bought the recycled plastic foundation beams as these would never rot. Getting these cut to the right size and angle was actually quite a challenge as they are just slightly too big for my mitre block. In addition, as they only comes in 3m length I had to join them for all 4 walls – well 3 actually as the front has the gap for the door anyway. Given the importance of getting the foundation absolutely squared, this was IMO the most critical step in the entire build. With the unpacking/checking and moving the logs into the garden ready for the build, setting the foundation layer took me into the following day. In fact, it took me almost another 2 hours the next day before I was happy to proceed. I also had the help of my lovely wife to check the squareness of the base layer as once it started going up, you don’t want to undo it!

Log Cabin Base

Before I started the build, I also laid down a layer of DPM (plastic membrane used to prevent rising damp). I know the advice was only to lay it under the foundation pieces and then, once the build is completed and the floor is ready to be laid, to add the floor covering at that stage since it could get punctured during the build. To be honest, the DPM did get a bit battered with all the foot traffic but they stayed intact. In any case they were cheap enough that I bought twice the required amount which allows me to have a second layer once I am ready to install the floor. With 2 layers of DPM I think I am pretty protected from rising damp!

Jenny Cabin Installation With DPM

Once the foundation layer is in place, the walls go up surprisingly quickly. You do need a good (heavy) rubber mallet for this which was something I found invaluable. I bought a 32oz (about 1kg) white rubber mallet just in case my (smaller) black one would leave marks but was very glad for the heavier mallet, which really help to hammer the logs into place. The few pieces that were warped were helped into place using a couple of good, strong Irwin Quick Grip XP clamps. The door frames (which needed to be put together from the 4 separate pieces) goes in after 5/6 layers of wall logs. BTW, be careful when putting together the door frame especially the stainless metal covering the bottom piece – it is very sharp and will easily slice your fingers. Don’t ask how I know.

The windows go in once you get up to the right level. Be sure to get the window frames down squarely and adequately as if not, you may find later that the first full length log will not fit. It had me scratching head for quite some time before I figured this out.

This slideshow requires JavaScript.

Once the final wall logs are in place, it is time to fit the apex logs. At first, I was worried that it would be in one piece (which can be quite heavy) as you will need to raise it quite high. However, it comes in normal, log size pieces which interlocks into each other via T&G so quite easy to install in the end. Installing the long roof purlins fixes the apexes in place and make the whole structure very stable. Next step is installing the roof boards!

Jenny Roof Purlins

Installing the roof was the most onerous job in my build. The fact that the cabin is sited close to the edge of our property and under the existing hedging conifers (which I wanted to keep as much as possible) means that one half of the roof had to be installed under the conifers. Installing the roof boards was actually not so hard as you can do this from inside the cabin using a step ladder/platform, but the roof shingles was an entirely different challenge. Also, because of the proximity of the conifer I ended up having to jigsaw off about 5cm along the entire length of the roof once it was already in place – due to the proximity of one of the conifer tree.

This slideshow requires JavaScript.

Once the roof boards are on, it was time to install the shingles. These came free with the cabin and we got the rectangular one. We would have preferred the hexagonal shingles but as it is free, one cannot complain. This took quite some time to complete especially the half that is under the conifers. I had to crawl along the roof under the conifers with very little headroom whilst measuring, cutting and nailing the shingles in place. It was the hardest part of the build but also a tremendous sense of achievement once completed. I have to admit the shingles really finish off the cabin in fine style.

This slideshow requires JavaScript.

We also bought the floor kit with the cabin, since this finishes off the cabin nicely. The thought of using OSB boards after the personal effort and attention of the build makes me cringes. As the floor is inside, there was no real rush to do this but unfortunately, there were a couple of weekends of heavy rain so exterior work has to wait. The floor boards were installed in a similar fashion to the roof boards (in fact, I think they are the same except for the numerous finger joints that exist with the floor boards) but here you have to cut all the boards at exactly the right place in order to ensure both pieces can be supported by a floor joists at the joint. I used plenty of nails and luckily there were plenty supplied.

I was really keen to ensure the exterior of the cabin is protected ASAP. For this we got Sickens Rubal Saturn Plus in a specially mixed colour, with complimentary shade for the door and windows. These are the “thickest” protectant we could found which is recommended by Tuin. We also got the Rubal Undercoat to make sure the final colour is nice and uniform and to give it 3 coats in total – I don’t intend to have to repeat this in the future and the attention and details will only be justifiable when the whole thing is “nice & new”. These paints were really good – nice and thick with strong opacity but boy, they do take some effort. Luckily, there were quite a few days of good sunshine, but I had to take extra days off work just to make sure the painting was completed.

This slideshow requires JavaScript.

With everything completed, it was time to deal with the interior. We wanted to keep the natural wood look inside but thought it best that the floor is protected. Unfortunately, there doesn’t seem to be clear equivalent of the Sickens Rubal, so we ended up with Tuin’s own recommended Carefree Protectant Timber Treatment. We don’t need that much but as you have to order 2 tins, we thought that if they are anywhere as good as claimed, we would be more than happy to use them for our garden furniture as well. Applying the Wood Protectant to the floor was very quick and the Protectant goes on extremely easily – almost like painting on water in fact. Once we have applied one coat of the Wood Protectant we apply another, normal coat of wood varnish to reduce wear. This also gives it a slightly darker shade, which is actually quite nice.

Overall, I am very pleased with the quality of the Jenny Log Cabin and the service from Tuin. I would definitely recommend Tuin for their quality cabins which are quite reasonable price-wise. The free shingles, if you get them, is a no-brainier and really completes your build.

A few thoughts and tips from my experience:

  1. Use some good, large brushes when applying the protectant to the exterior. There is so much surface that you will be glad to have a decent brush which can cover the area quickly.
  2. Be careful when installing the Georgian door & window frames. The frames are very simple wood strips which you have to nail to the door/windows. They are not bespoke made so can leave some doubts as to how they fit. In addition, they are not really long enough thus leaving little space to put the nail. In fact, I cracked both my window panes as the nail hits the glazing. With hindsight I now understand why so many of the builds do not have these frames installed (even on Tuin’s own website).
  3. I would recommend getting the best wood protectant you can find. The amount of work required to do this will outweigh any cost considerations and you will regret using cheap stuff (or just end up doing a sloppy job).
  4. Get a decent rubber mallet (ideally white so that it doesn’t leave marks).
  5. Make sure you have a good set of strong quick grip clamps as you will need these when installing warped logs or the roofing eave slats. They are also an extra pair of hands which you will find invaluable at times.
  6. Take your time with the roof shingles (if you are using them). They take some time to install but the quality and appearance of a well laid roof shingles really add the cherry to the cake.
  7. With the cost of the cabin and effort required to build, I would strongly recommend getting at least 2 layers of DPM so that the interior and floor are protected from any rising damp. They are also not expensive.
  8. You will most likely need an impact driver to install the first layer of logs onto the foundations beams. If not be prepared for some cursing and sore hands.

If you do decide to go for one of these log cabin, be prepared for some real hands-on action and I hope the above write-up would provide some assurance. I am a reasonable DIYer but nothing in this build can be considered difficult. The initial start is the most anxious part but once you are on your way, it is really not that difficult – certainly within the capability of most competent DIYers. The satisfaction and sense of pride after its completion, however, will be there to enjoy for decades thereafter. Good luck with your build.

This slideshow requires JavaScript.


Thank you to Mr T for such a lengthy and informative review! As for some of your confusion that you guys may have with the window and door frames- They are for decoration purposes and aren’t very thick in terms of the timber. For the Georgian look you will have to be careful with installing them, some people tend to opt out for them as they don’t like the look- But they are featured on some of our showsite buildings!

Why not look into the Jenny Log Cabin for your unique garden canvas?

For more in depth customer reviews such as Mr T’s, browse through our Pictorial Customer Reviews.

Lauren Clockhouse Log Cabin Review

One of our customers was very generous in sending a review of their Lauren Clock House Log Cabin (previously known as the Special Ben), with plenty of images to show you guys the installation progress! We do love receiving images here at Tuin, so thank you Mr F for sending this to us!


Mr F writes as follows:

We were both extremely impressed with the quality of the material and the thought and precision that had gone into the preparation of the kit of parts.

This slideshow requires JavaScript.

The 1st of 3 packages arrives, expertly manoeuvred by Barry, the truck driver. Each load was 20ft long and weighed about 1.7tons. By the second image there was a total of 5 tons of shed. Due to a lack of planning on my part they were going to remain unwrapped for about 2 weeks as the ground work was completed.

Work starts on the base about 08.00hrs. Quite a bit of soil had to be removed to
give us a level area. A load of scalping is delivered to the pit, in all, 12 tons was used to form a base for the cement.

This slideshow requires JavaScript.

Kharn, the builder, with his whacker plate consolidates the scalping and the
shuttering is leveled. We finished at 20.30hrs – a long day but the pressure was on as we had booked the ready mix lorry for 08.00hrs the next morning.

Leveled Out Shuttering

Impressive work in just one day Kharn!

Day 2 at 07.55hrs, 13 tons of cement arrives… A small dumper truck was used to bring the cement to the site and frantic tamping continued for over 2 hours until all appeared level – very hard work!

A couple of days later and with the concrete hardened the rear bank was ‘landscaped’ and a trench for gravel dug at the base.

This slideshow requires JavaScript.

Monday, Day 1 of construction at about 08.00hrs. The lower beams had been treated the day before and the black items are lengths of the plastic base material. The walls progressed nicely and the plastic base strips have just been cut to fit and slid under the lower logs. Note the log which will eventually be fitted above the door, has been temporarily positioned to keep things square despite the gap in the front wall.

This slideshow requires JavaScript.

How the joints between the front and rear wall and the middle wall were to be made was a mystery to us but the long logs with vertical holes near the joints gave us a clue and answered the question, ‘what were the square pegs for?’.

The square pegs or ‘wall dowels’ had their corners and ends rounded slightly which still resulted in a satisfying tight fit but with less chance of splitting the logs. The 3 on the left have been treated with a belt sander. About 1 minute per peg and about 60 pegs in total. A pencil mark at the halfway point was useful when banging in.

Wall Dowels

Don’t worry Mr F, these can confuse most people!

About 12 hours after we started and we realise that it’s quite a big Log Cabin!

Installed Walls

The Lauren Clockhouse Log Cabin is one of our longest products!

Day 2 and the roof is progressing well. For the first 2 days of construction there were 3 of us working with lots of carrying from storage area to site and quite a bit of head scratching as we searched for various specific logs. Three pairs of hands were useful as we positioned and fixed the heavy purling.

A start is made nailing the tongue & groove roof boards into position. Much later and all of the boards are fixed. Rain was expected so we protected the roof. Probably no need to but it made us feel better.

This slideshow requires JavaScript.

Day 3 was mainly spent nailing floor boards. The nail gun chose a bad time to fail and resulted in much manual hammering. Day 4 was mainly spent fixing shingles to the rear. A slow job but looked good when done. Ladders R Us.

This slideshow requires JavaScript.

Day 5, the small gable comes in 3 pieces which we screwed together at ground level then lifted into position. Inevitably, it complicated the fixing of shingles on the front and it was quite late on the Friday before we finished. On days 4 & 5, some time was spent hiding from the heavy showers which slowed us down a little.

We used some heavier timber to trim the base of the roof to provide a substantial mount for guttering. Note the notches required to fit it around the left, right and middle wall. With a bit more thought I could have cut the timber longitudinally to a better shape for the gutter brackets but now I’ll have to custom make a mounting for each bracket.

This slideshow requires JavaScript.

End of day 5. It looks like the finished product but still needs a lot of detail work and much brushwork. The most important pieces of paper. A list of contents annotated by me with the log positions and the detailed diagrams showing each log position.

This slideshow requires JavaScript.

Happiness is 3 empty pallets. Progress would have been quicker if I were able to unpack and lay out in piles all the various bits of timber. The sheer quantity of wood (and the animals in the field) precluded that, so quite some time was spent rummaging for specific pieces as required. The timber had been cut very accurately and we found that the lengths on the plan, accurate to the millimeter, were very useful in identifying the required log.

Empty Palettes

True happiness indeed!

As garden buildings go, this was a big project and I wasn’t too surprised that the main build took 5 days. Kharn, a professional builder, and I were very impressed with the quality of the material and the accuracy with which it had been prepared. The joints were well thought out and accurately milled although we were dealing with significant lumps of timber and found a club hammer, with protective wood, more useful than a mallet! Even a sledge hammer was found a use in squaring-up the part built walls. Apart from the nails in the floor and roof boards, and the wall dowels, virtually no other fixings were used. The wall logs and purlins stay in position because of the clever joints while the entire building sits steady on its base because of its weight. The packing had been very well done and, as far as I am aware, no parts were missing. Indeed, the supply of plain wood parts seemed generous. Although
there were 450kg of shingles we were a little concerned that we would run out. With 378 shingles we finished the roof with 2 remaining – very well judged by the manufactures.

Overall, I’m a very happy customer and, more importantly, so is my wife! An outstanding product at a bargain price. As the Americans would say, ‘A lot of bang for your buck’. Many thanks for the excellent service and the experience of the build has got my builder friend thinking of buying a smaller version for himself. I hope to have the staining and guttering done soon and will send you a picture of the finished item.


Thank you again Mr F for a detailed and informative overview of your installation process for the Lauren Clockhouse Log Cabin. It looks great and we can’t wait to see your pictures for when it’s completely finished! I hope you and your wife enjoy your log cabin!

Other customer experiences, build articles and tips can be found at: Pictorial Tuin Reviews.

Rosenheim Log Cabin Build Review

We have recently received this review from Mr B of how he installed the Rosenhiem Log Cabin for the perfect shelter for his hot tub! Thank you for showing us your impressive work with the installation of your Log Cabin, we hope you enjoy the Rosenheim and your gift for many years to come!


Mr B writes as follows:

We decided on Tuin for our log cabin after a long 6 months search for the best cabins and every time Tuin kept coming back to the top of the list so we decided with the start of our extension build and the need for the cabin for the hot tub we would finally bite the bullet and order.
We were not disappointed!

Day 0 : Base Construction
As we were having an extension built we paid the grounds workers to lay us a flat 4m x 4m concrete slab. I had originally planned to build a deck base but once I worked out it would need to support over 3 metric tonnes I decided my construction skills may not quite have been up to the job and that the cement slab would be better (plus as it turns out cheaper!)

Setting Up The Base

Sometimes getting help for installing makes it less stressful!

Day 1 : Day of Delivery
8pm we received a phone call from a nice Dutch lorry driver to say that he had managed to get most of the way onto the housing estate we lived on but couldn’t get all the way in his massive 44 foot lorry! I walked down to help unload and escorted him as he drove the Moffett carrying a very long 5.3m package. Unfortunately whilst our drive was 4m wide it really needed to be 4.10m for him to have been able to place it neatly on our drive so after a conversation with our neighbour the cabin was stored across our drive and the neighbour’s garden. A cuppa later and nice Dutchman was back on his way.

Day 2: 6:15am – Day of Construction
Woke up early as keen!

The Log Cabin Delivered

All here and ready to go!

It takes a long time (1hr 45mins) to move all that wood just 10m to the back of the house but important to get it all close to hand and sorted by type.

Day 2: Approx 10am
It’s starting to take shape – fortunately I was able to second one of the builder’s apprentices to lend me another pair of hands so once the foundation beams were all set up and checked to be completely level the logs went on very easily. In the entire build only had two mildly warped beams that needed a little extra persuasion.

Day 2: Approx 1pm
Roof beams all on now and just starting to fit the roof boards. We had opted for an extra side window that you can see here so we had cut out the logs as we went (watch out for jigsaws they are sharp! – My cabin is now permanently marked with the blood of my endeavours!)

Day 2: 3:15pm
Roof boards all on and time to call it a day as wanted to start a fresh putting the roof felt tiles on.

An impressive days work!

Day 3: 8am – 4pm
Long hot day in the blazing sun but got all the roof tiles on – takes a little time to get the first row level and done but then they all just flow from there. Nice sturdy roof that easily took my 15st.

Rosenheim Fully Installed

Second Day of Installing

Day 4 – 6 – The paint job
This was the worst job of the entire task. As we were using it for a hot tub cabin we had been warned to use impregnation fluid (2 coats) on the inside – as this is clear it is very hard to see where you had done so had to be methodical . Once that was on two coats clear treatment on the outside and additional 2 on the inside – Took approximately 36 hours of effort (2 of us at it ) – Don’t underestimate the amount of time this will take! But would completely recommend the treatment from Tuin as whilst it took a long time it went on easily and created a perfect finish.

One additional thing that is worth mentioning is that read all the blogs and suggestions on the main site – and follow the instructions – don’t be tempted to not!
Finally the cabin was finished and we could commission the hot tub and start relaxing. The rest of the photos show the end result – we are very pleased so much so that we have recommended Tuin to lots of our friends who are starting to make their own enquiries and I am sure will shortly be Tuin owners.

The Rosenheim Fully Painted

Tada!

Rosenheim Interior

A perfect fit!


The Rosenheim Log Cabin turned out to be a perfect fit for a hot tub! I personally love how the lighting from the hot tub really sets the mood inside- the ideal atmosphere for a relaxing session!

Thank you to Mr B for sending this in! We always love to see how many ways a Log Cabin can be put into use!

Interested in more reviews like Mr B’s? Find more on the: Tuin Pictorial Customer Reviews.

Shed of AWESOME

So, we’ve recently been sent over this blog, where Williem from The Secret Batcave tells us of his journey, or in his words- a tragedy, on building the SHED OF AWESOME – This is Willem’s own blog.

He originally was planning to build his own shed/log cabin, with parts I and II showing us his layout plans and building considerations. But alas, his wife won this case with our five star rated Yorick cabin.

This slideshow requires JavaScript.

In part III of his quest he talks about how he came across Tuin and what made him go for the Yorick Log Cabin, even considering the tears of any tall person who has used other garden offices that unlike ours, have a shorter roof height. The comment about the tall people is really what had me sold on this series of posts (I had originally read part III first) Williem’s humour can reach into any situation! A humour that reminds me of Richard’s with a slither of mine in too. A little more extreme though. Needless to say, a fantastic combo.

Before you click through though, please note there is some colourful language. We cannot be held responsible for Willems website content which can be lively at times and may offend some people.

His posts come with step by step images of how he built his Yorick log cabin, any challenges he faced and how he overcame them. This was definitely an interesting read!

Finished Yorick

The fully built Yorick Cabin before insulation!

We’ll definitely be keeping an eye on this blog for anymore updates, until then you can enjoy part I, part II, part III, part IV, part V and part VI.

Thank you Willem for sending this to us! We hope you and your wife enjoy the Yorick Log Cabin!

Please note: Willem uses some colourful language in his posts of which we are not responsible for. Click through if you wish but please note my warning.

Julia Log Cabin

We have received a customer review from Mr P of their experience with installing their Julia Log Cabin. Thank you for sending this in!  We love how the bar turned out- It’s a great idea!


Mr P writes as follows: 

Back in February I purchased a Log Cabin from Tuin.

Several months later I have completed the project, turning it into a bar and brewery. Very pleased with it and your customer support and thought I would share some pictures with you!

This slideshow requires JavaScript.

 


We love the bar and brewery Mr P! Thank you for sending in your images, we hope the brewing turns out well!

Other customer experiences, build articles and ideas can be found at: Pictorial Tuin Reviews.